DUBAI Metro

Key Points

  • Project name : DUBAI METRO
  • Owner : Road and Transport Authority Dubai
  • Consultant : WS Atkins
  • Main Contractor : JTMETROJV
  • Total Weight : 9,200 Tons
  • Area (m)2 : 43,000
  • Location : Dubai, UAE
  • Year of Construction : 2008
  • Duration : (Connection Design and Fabrication) 8months
  • Status : Completed

Description

EBS executed Concourse Steel work fabrication for 4 Red line stations and 6 Green line stations. The Length of each Station is 130 m & width varies from 15.5m at the ends to 26.5m at the middle of station. The Concourse steel work consist Cantilever girders of size 1800mm wide x 105mm thick tapered flanges & 1600mm deep x 25mm thick tapered web. These girders of length 11.2m (max) are cantilevered off the central via duct on either side using Tension strap plates at top & using anchor bolts at the bottom. These girders, together with the in-between Secondary beams support the concourse RCC slab with metal decking. Connection Design and Fabrication are in EBS Scope of Work.