Khurais Water Injection Facilities and Utilities Project

Key Points

  • Owner : Saudi Arabian Oil Company
  • Consultant: Foster Wheeler Energy limited
  • Main Contractors : Snamprogetti
  • Total Weight : 4,150 Tons
  • Area (m)2 : 24,428
  • Location : Khurais, KSA
  • Year of Construction : 2007
  • Duration : (Detailing and Fabrication) 8 Months
  • Status : Completed

Description

Construction of a two pumps trains and seawater injection pump train, plus related facilities, which forms a key part of the Khurais oilfield development program. The injection plants will have a capacity of injecting over four million barrels of treated seawater per day. The Khurais field, with an area of 2,890km² and 127km long. Detailing and Fabrication are in EBS scope of work.